WE Report

Lessons Learned

Lesson Learned





By: Lars Solvang

Report No.

2173

Discipline/Origin

Subsea
Own Experience

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2021/10/01
1528 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Equipment
Negative

Borgland Dolphin


What happened in P&A:
Weight of the black eagle hose will make alignment to the manifold flushing cap difficult.

What Was Planned

Connect a 2″ black eagle hose to the spare high pressure hub on the manifold.

What Was Learned

Remove the hydraulic penetrator pins from the hub. This enables the hub to be rotated and still be able to engage to the hub.

What Actions Are Required

Remove the hydraulic penetrator pins from the hub.

EDITOR


CLOSE LL (testing)





New Lesson Learned

You do not have permission to view this form.